China National Electric Wire & Cable Imp./Exp. Corp.

Google

2 Scope of Work

The scope of works of the power plant includes design, manufacture, supply, procurement, erection, test and commissioning of the geothermal power plant on EPC basis, and also basic design of civil workls.

2.1Civil Works

Basic design of civil works including following items and civil work supervising,

a) Foundation and loading design and calculation for building

b) Foundation and loading design and calculation for main equipment

c) Foundation design and calculation for cooling tower

d) Foundation design and calculation for water tanks

e) Foundation design and calculation of condenser

f) Foundation design and calculation for other equipment

g) Design of inner size of all building

Design for connection of beam, pile, cross-section

Design for location and size of doors, holes etc.

2.2 Mechanical works

B-1 Turbines

Condensing steam turbines (single flow and skid mounted type), with attached stop valves, governing system, oil control and lubrication system, moisture separation and dryings, turning gear, over-speed detection, vibration monitoring, safeties and protections, steam by-pass system and its silencers.

B-2 Steam piping & demisters

Steam piping, valves, with demister on the principles of vane separation, water injection system for removing silica on turbine inner space and blades.

B-3 Jet Condensers

Steam condensers, direct contact, spray with water mixing type with internal features for functions of steam condensing, condensate water cooling and non-condensable gas extraction including hot well pump

B-4 NC gas extraction system

Non-condensable gas (NCG) in the steam of content up to 3% in weight of steam flow extraction system for removing it (by vacuum pump) from turbine exhaust steam

B-5 Cooling water system

Main water cooling system complete with piping (fiberglass reinforced polyester), fittings, filters and pumps, control system, cooling tower (counter flow type or cross flow type, mechanical induced draft, with splash fill) including reinforced epoxy-coated concrete basin, fan stack (made of fiberglass reinforced polyester (FRP)), drift eliminator, infill, water distribution system, mechanical equipment

B-6 Re-injection water system

Pumps, pipes and associated equipment

B-7 NaOH dosing system

NaOH storage tank (10m3) and control valves

B-8 Service water supply

Water storage tank, filters, pumps, pipes (incl. Pipe river to power plant, 500m) associated equipment (service water to be used for initial fill of water cooling basin and fire fighting system)

B-9 Fire fighting

Fire detection system, fire fighting water system included hydrant network and pipes, and water spay extinguishing system on turbo-generator lubricating units and main transformers, portable and mobile fire extinguishers

B-10 Handling equipment

Overhead traveling crane (electric controlled) including structures, rails, hoists and associated equipment, mobile handling and lifting devices and equipment

B-11 Laboratory and Personnel safety equipment

Chemical analysis laboratory, H2S detection and protection system

B-12 Workshop equipment

Special tools and devices for turbine and generator, common tools and appliances

B-13 Ventilation and air conditioning

Ventilation and air conditioning

2.3 Electrical works

C-1 Generators

Generators with neutral grounding and excitation system, generator main electrical output system

C-2 Transformers

Main transformers and station transformer

C-3 Medium voltage system

Switchgears

C-4 Low voltage system

Switchgears

C-5 Control and monitoring system

Computer system with logic control system for control and supervision including one video display unit printer, back-up vertical panel for conventional (manual) control of main functions, protection system.

C-6 Protection system

Protection system for electric and mechanical equipment

C-7 Exigency serviced system

Diesel generator, DC power system, UPS

C-8 Lighting and earthing

Lighting and earthing system

2.4 Others